The Reality of “Pulling” Equipment Early
In theory, projects aim to “pull” equipment when it’s needed.
In practice, many project teams request delivery earlier than required to avoid the risk of delays. That buffer may be a week, a month, or more.
The intent is understandable. No team wants to delay installation because equipment hasn’t arrived.
But pulling equipment early often leads to:
- …Additional staging and rehandling, with each additional lift increasing operational risk and the potential for equipment damage
- …Congested job sites or offsite storage areas
- …Equipment being managed without structured tracking or systems
At that point, the project hasn’t eliminated risk; it has shifted it.
Instead of worrying about late delivery, teams are now managing early inventory without clear visibility or sequencing.